Schedule: May 2013 to September 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be widened to the 32-foot City standard.
August 26 to August 30: The paving subcontractor will place the asphalt pavement. The landscaping subcontractor will occasionally water the restoration areas.
Traffic Impacts: Fourteenth Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Grace Avenue from Woodland Avenue to Sunset Circle
Schedule: June 2013 to September 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be widened to 28-foot.
August 26 to August 30: Crews for Alliant Energy will complete gas service transfers. The excavation subcontractor may begin general excavation and placement of the stone base.
Traffic Impacts: Grace Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Sunset Circle south of Grace Avenue
Schedule: June 2013 to September 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be 29-feet wide from back of curb to back of curb.
August 26 to August 30: Crews for Alliant Energy will complete gas service transfers. The excavation subcontractor may begin general excavation and placement of the stone base.
Traffic Impacts: Sunset Circle is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours. North Main Street from Scott Street to Frazier Drive
Schedule: July 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, storm sewer, street, and lighting on the east side of the street only.
August 26 to August 30: The utility contractor will complete installation of storm sewer main and structures. The excavation subcontractor will begin general excavation and placement of the stone base. The electrical subcontractor will install electrical conduit crossings. The concrete paving subcontractor will begin preparation for concrete pavement paving. Concrete paving will occur between Scott Street and Harbor View Drive.
Traffic Impacts: North Main Street is closed to through traffic and closed completely to northbound traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Auburn Street from Brooke Street to Termini
Schedule: August 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be widened to the 32-foot City standard.
August 26 to August 30: The utility contractor will begin installation of sanitary sewer. The contractor will begin in Brooke Street and work toward the west.
Traffic Impacts: Auburn Street is closed to through traffic. Brooke Street will be closed to all traffic at the intersection with Auburn Street until the completion of the underground utilities. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on Auburn Street during working hours.
Everett Street from Sheboygan Street to East Division Street
Schedule: September 2013 to October 2013
Description: The project includes reconstruction of the water main, partial storm sewer and partial street.
August 26 to August 30: No work this week.
Traffic Impacts: Everett Street remains open to traffic.
Champion Avenue from East Division Street to Merrill Avenue
Schedule: September 2013 to October 2013
Description: The project includes reconstruction of the water main, partial storm sewer and partial street.
August 26 to August 30: No work this week.
Traffic Impacts: Champion Avenue remains open to traffic