Division
Street from Brooke Street to Gould Street – Street Closure
Schedule:
June 17, 2013 to June 21, 2013
Description
& Traffic Impacts: West Division
Street will be closed to through traffic between Brooke Street and Gould Street
beginning Monday June 17th through Friday June 21st due to the relocation of
the Well’s Manufacturing facilities. Semitrailers will be parked on Division
Street between 7AM and 4 PM loading heavy equipment for transportation to the
new location. The street will reopen to regular traffic each evening after 4PM.
The public is asked to plan an alternate route as there will not be a marked
detour.
Kaye
Street from Eleventh Street to Thirteenth Street
Schedule:
April 22, 2013 to June 2013
Description:
The project includes reconstruction of
the sanitary sewer, water main, storm sewer, street, and lighting. The street
will be widened to the 32-foot City standard.
June
17 to June 21: The electrical
subcontractor will continue installation of wiring and light poles. The landscaping
subcontractor will begin terrace restoration.
Traffic
Impacts: Kaye Street is closed to through traffic.
It is illegal to drive past a “ROAD CLOSED” sign or to move any construction
barricades. Residents, business owners, and customers may access properties
past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the
street during working hours.
Fourteenth
Street from South Marr Street to South Park Avenue
Schedule:
May 2013 to September 2013
Description:
The project includes reconstruction of the
sanitary sewer, water main, storm sewer, street, and lighting. The street will
be widened to the 32-foot City standard.
June
17 to June 21: The utility
contractor will continue installation of storm sewer.
Traffic
Impacts: Fourteenth Street is closed to through
traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any
construction barricades. Residents, business owners, and customers may access
properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not
permitted on the street during working hours.
Grace
Avenue from Woodland Avenue to Sunset Circle
Schedule:
June 2013 to September 2013
Description:
The project includes reconstruction of
the sanitary sewer, water main, storm sewer, street, and lighting. The street
will be widened to 28-foot.
June
17 to June 21: No work this week.
Traffic
Impacts: Grace Avenue remains open to traffic.
Sunset
Circle south of Grace Avenue
Schedule:
June 2013 to September 2013
Description:
The project includes reconstruction of
the sanitary sewer, water main, storm sewer, street, and lighting. The street
will be 29-feet wide from back of curb to back of curb.
June
17 to June 21: No work this week.
Traffic
Impacts: Sunset Circle remains open to traffic.
North
Main Street from Scott Street to Frazier Drive
Schedule:
July 2013 to October 2013
Description:
The project includes reconstruction of the
sanitary sewer, storm sewer, street, and lighting on the east side of the
street only.
June
17 to June 21: No work this week.
Traffic
Impacts: North Main Street remains open to
traffic.
Auburn
Street from Brooke Street to Termini
Schedule:
July 2013 to September 2013
Description:
The project includes reconstruction of
the sanitary sewer, water main, storm sewer, street, and lighting. The street
will be widened to the 32-foot City standard.
June
17 to June 21: Crews for Alliant
Energy will continue installation of gas main and services.
Traffic
Impacts: Auburn Street remains open to traffic.
Traffic may be temporarily restricted while crews are at work.
Everett
Street from Sheboygan Street to East Division Street
Schedule:
September 2013 to October 2013
Description:
The project includes reconstruction of
the water main, partial storm sewer and partial street.
June
17 to June 21: No work this week.
Traffic
Impacts: Everett Street remains open to traffic.
Champion
Avenue from East Division Street to Merrill Avenue
Schedule:
September 2013 to October 2013
Description:
The project includes reconstruction of
the water main, partial storm sewer and partial street.
June
17 to June 21: No work this week.
Traffic Impacts: Champion
Avenue remains open to traffic
No comments: