Friday, September 20, 2013

9-21-13 fdl street reconstruction update

Johnson Street turning lanes at Country Lane
Schedule: September 2013 to October 2013
Description: The project includes construction of a left and right turn lane from Johnson Street to future Country Lane to the south. The construction limits are approximately 500 feet east and west of Country Lane.
September 23 to September 27: Work will continue on both the westbound and eastbound lanes of Johnson Street.
Traffic Impacts: Traffic on Johnson Street will be restricted to one lane in each direction. Country Lane and the driveway to the shopping plaza will remain open.
Grace Avenue from Woodland Avenue to Sunset Circle
Schedule: June 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be widened to 28-foot.
September 23 to September 27: The electrical subcontractor will continue electrical conduit installation.  Once completed the electrical subcontractor will install wiring and place light poles. The concrete subcontractor will begin replacement of driveway approaches, sidewalk panels and curb ramps.
Traffic Impacts: Grace Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Sunset Circle south of Grace Avenue
Schedule: June 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be 29-feet wide from back of curb to back of curb.
September 23 to September 27: The electrical subcontractor will continue electrical conduit installation. Once completed the electrical subcontractor will install wiring and place light poles. The concrete subcontractor will begin replacement of driveway approaches, sidewalk panels and curb ramps.
Traffic Impacts: Sunset Circle is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
North Main Street from Scott Street to Frazier DriveSchedule: July 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, storm sewer, street, and lighting on the east side of the street only.
September 23 to September 27: The electrical subcontractor may begin installation of conduit mid to end of the week.
Traffic Impacts: North Main Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Auburn Street from Brooke Street to Termini
Schedule: August 2013 to October 2013
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting. The street will be widened to the 32-foot City standard.
September 23 to September 27: The concrete subcontractor will begin preparations for placement of curb and gutter. The concrete subcontractor may also prepare and place concrete pavement in the intersection with Brooke Street.
Traffic Impacts: Auburn Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on Auburn Street during working hours.
Champion Avenue from East Division Street to Merrill Avenue
Schedule: September 2013 to October 2013
Description: The project includes reconstruction of the water main, partial storm sewer and partial street pavement.
September 23 to September 27: The utility contractor will continue water main installation.
Traffic Impacts: Champion Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on Auburn Street during working hours.
Everett Street from Sheboygan Street to East Division Street
Schedule: September 2013 to October 2013
Description: The project includes reconstruction of the water main, partial storm sewer and partial street pavement.
September 23 to September 27: No work
Traffic Impacts: Everett Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on Auburn Street during working hours.