The Scott Street Bridge will
temporarily re-open for vehicle and pedestrian use due to forecasted rain the
entire week. The contractor performing
the epoxy deck and sidewalk sealing estimates three additional working days with dry conditions are necessary in order to complete the
work. The bridge is scheduled to close again at 5 am Monday, June 23rd. The detour route will remain in place during
the temporary reopening. The posted detour route for USH 45 is Northbound traffic on USH 45 will
detour from North
Main Street, west on Johnson Street, north on Peters Avenue, east on Scott
Street and return to northbound USH 45 at Lakeshore Drive. The southbound detour will be opposite route. Bus service on Scott Street will be
moved to Arndt Street from Brooke Street to Hickory Street.